Project Plan:
Collect Requirements: 1/6/2014 to 1/10/2014
Design Solution: 1/13/2014 to 1/14/2014
Construct Solution: 1/15/2014 to 1/17/2014
Unit Test: 1/20/2014 to 1/24/2014
Integration Test
Release to Production: Target date 2/1/2014
Implementation